CREAM III Flight Trajectory

Click the map below to see the CREAM III flight trajectory.

CREAM III flight trajectory

CREAM-III Major Milestones

01/04 TCD mechanically integrated
01/25 CherCam+CD mechanical fit-check
04/26 CherCam T-Vac test completed
04/30 Instrument mechanical integration complete
05/01-07/08 Electronic & data integration & testing
07/09 Instrument delivered to WFF (truck incident)
07/09-09/06 CREAM payload integration & testing
09/07 Mission Readiness Review
09/16 CDM & Ground support equipment shipped out of WFF
09/28 SFC1 replaced with SFC3
10/05 Last access to instrument
10/15 Instrument & shipped out of WFF
11/11 Science & WFF crew arrive McMurdo
11/12 GSE delivered to payload building
11/13 Instrument delivered to payload building
11/15 Instrument CPT completed
11/17 Joint LPT completed
11/19 End-to-end data flow test
11/27 Batteries delivered to payload building
12/03 Ready for hang-test
12/04 Hang test
12/04 Flight Ready
12/19 Launch

Jan. 17 2008 (NZT): Termination of the flight
Jan. 29 2008 (NZT): 1st recovery flight (Twin Otter)
Feb. 1 2008 (NZT): 2nd recovery flight (Twin Otter), 3rd flight from Siple dom (Twin Otter) Completion of recovery